Mumbai Infra Update: MSRDC To Appoint Separate Contractor For ₹1,722-Crore Pali Hill Sea Link Connector
· Free Press Journal

Mumbai, October 9, 2026: The proposed 3.55-km Pali Hill connector to the Swatantryaveer Savarkar Sea Link (Versova-Bandra Sea Link) will be developed as a separate project, with the Maharashtra State Road Development Corporation (MSRDC) planning to appoint an independent contractor after obtaining Coastal Regulation Zone (CRZ) approvals, said Anil Kumar Gaikwad, chief officer, MSRDC.
The project aims to improve connectivity between the sea link and Bandra West, particularly Pali Hill, where narrow approach roads and heavy traffic frequently cause congestion. Motorists currently take around 20-30 minutes to cover the 2.6-km stretch from the sea link toll plaza to Pali Hill, with approach roads largely restricted to a single lane in each direction.
Visit sportbet.reviews for more information.
Government Approval And Project Cost
The state government has already granted administrative approval for the connector, proposed as an additional road link to the sea link near Bandra Fort, opposite Hotel Taj Lands End.
According to a government resolution dated July 28, the project is estimated to cost Rs 1,722.40 crore, including Rs 1,183.79 crore for civil construction. The remaining amount will cover allied provisions and GST.
Four-Lane Connector Planned
The four-lane connector, with two lanes in each direction, will extend 3.55 km, including the main carriageway, ramps and loops. The main carriageway will measure 1.269 km, while the design includes a 175-metre loop and ramps ranging from 214 metres to 365 metres.
MSRDC had submitted the proposal to the public works department on August 19, 2024, following demands for improved traffic circulation around Bandra Fort and the sea link.
The connector is expected to provide an alternative route for motorists heading towards Pali Hill, reducing pressure on existing roads.
Also Watch:
FPJ Dialogue: MSRDC Aims To Develop 6,000 Km Of Expressways, Related Infrastructure By 2047, Says MD Dr Anilkumar GaikwadKey Statistics
3.55 km – Total connector length
Rs 1,722.40 crore – Estimated project cost
Rs 1,183.79 crore – Civil construction cost
4 – Traffic lanes
1.269 km – Main carriageway length
20-30 minutes – Current travel time for 2.6 km